What Happens If You Win and Cannot Get the Performance Bond

This is the scenario the bid guarantee exists for, and it is worth being blunt about, because it is the most expensive thing that can happen to a contractor at the small end of surety.

The sequence

You bid. You win. The contract requires performance and payment bonds as a condition of award. Your surety, looking at the awarded scope rather than the estimate it saw at bid time, declines to write them.

The owner now does one of two things: it moves to the next acceptable bidder, or it re-lets the work. Either way it has a loss, and either way it calls your bid guarantee.

And then the part contractors do not expect. The bid guarantee is not your money. It is a surety’s undertaking, and when the surety pays the owner, you indemnify the surety. The call does not close the matter; it opens a debt.

Which is the fundamental asymmetry between a bid bond and cash bid security. Where an obligee takes a certified check — as Indiana’s Ind. Code § 5-16-5.5-2 and Oklahoma’s 61 O.S. § 1 both permit — the forfeited money is money you had. Where it takes a bond, the forfeiture creates an obligation you did not have before.

What it costs, federally

FAR 28.101-2(b) sizes the instrument rather than the loss:

“The bid guarantee amount shall be at least 20 percent of the bid price but shall not exceed $3 million.”

That is the ceiling on what the guarantee can be worth. The federal frame ties the requirement to the bonds themselves — FAR 28.101-1(a) requires a bid guarantee “whenever a performance bond or a performance and payment bond is required” — which is exactly why a solicitation asking for one is telling you the job is bonded work and your surety needs to be able to follow you.

What it costs, in the one state that says

Ohio is the exception that prices the outcome in the statute itself, and it does so two ways depending on what the owner does next: award to the next lowest bidder and the measure is the overpayment — the difference between your bid and theirs — capped at ten per cent; re-let the work instead and the measure becomes the administrative cost of running the procurement again, capped against the bid.

Two theories of loss for two owner responses, both capped, and which one applies is decided after you are already gone. The provisions themselves, and the reason the two caps are measured against different things, are set out in the Ohio bid guaranty guide.

One state lets you out

Ohio alone, in our reading, treats a bidder who has simply won more work than it can bond as something other than a defaulter. O.R.C. § 153.54(G) lets such a bidder withdraw — on a small public improvement, where another bid has already been accepted, and where the surety itself certifies that performing would exhaust the bidder’s bonding capacity. Both liability measures above are carved out for it, so a bidder inside the provision owes nothing.

What makes it unusual is not the relief but the evidence: the statute hands the capacity question to the surety and conditions the right on the surety being willing to answer it in writing. The conditions, the excluded agency and the reason the drafting is remarkable are set out in the Ohio bid guaranty guide.

Nothing equivalent exists federally. Under FAR 28.101 a bid guarantee is required because the bonds are, and running out of capacity between award and execution is your problem.

How the failure is actually avoided

The provisions above are remedies. The failure they remedy is nearly always the same and it happens before the bid.

A surety writing a bid bond is not underwriting the bid. It is underwriting the contract behind the bid, because the bid bond’s own exposure is precisely the cost of your failure to post the performance bond. A surety will not knowingly write a bid bond it would then refuse to follow.

So the useful conversation is the one where you tell your surety what you are about to bid, at what value, alongside what you are already carrying — and get a view on the whole thing rather than on the instrument in front of it. A contractor whose aggregate is nearly full is at risk on the second award of a season, not the first, which is exactly the situation Ohio wrote its subsection (G) around.

Where a single contract is larger than a surety’s single-job limit, Indiana’s Ind. Code § 5-16-5.5-2 offers a different route — incremental bonding, where multiple or chronological bonds together equal the total contract price, if the agency accepts it.

What this page does not cover

It does not state the bid-security rules for any state other than Ohio, and it does not address forfeiture of cash or certified-check security, which is governed by different provisions and different mechanics.

It also does not describe section 9.31 of the Ohio Revised Code, which § 153.54 names as a separate authorized reason for failing to enter into a contract and which we have not read.

Frequently asked questions

What happens if I win a bid and cannot get bonded?
The owner re-lets the work or moves to the next bidder and calls your bid guarantee for the loss. Because the guarantee is a surety’s undertaking rather than your deposit, you then indemnify the surety for what it pays — the obligation does not end with the call.
How much can a bid guarantee cost me?
On federal work FAR 28.101-2(b) sizes the guarantee at “at least 20 percent of the bid price but shall not exceed $3 million”, which is the ceiling on the instrument. States price the loss differently: Ohio caps liability at the difference between your bid and the next lowest, or ten per cent, whichever is less.
What if the owner re-bids instead of awarding to the next bidder?
In Ohio the measure changes. The bidder and surety are then liable for a penal sum not exceeding ten per cent of the amount of the bid, or the costs of resubmission — new contract documents, required advertising, printing and mailing notices — whichever is less.
Is there ever a way out without liability?
Ohio provides one. Under O.R.C. § 153.54(G), on a public improvement costing less than one-half million dollars a bidder may withdraw if another such bid has already been accepted, the bidder certifies in good faith that its current contracts total less than that figure, and the surety certifies in good faith that performing would exceed the bidder’s bonding capacity.
Does a bid bond get returned if I cannot proceed?
There is nothing to return — a bid bond is a promise, not a deposit. Where bid security was posted as cash or a certified check, that is money held and its treatment depends on whether the security was forfeited.

The failure is upstream of the award

Almost every version of this story starts the same way: a contractor obtained a bid bond for a job at the edge of its capacity and found out at award that the surety would not follow it to the full contract. A surety that writes your bid bond has already formed a view about the job behind it, and the moment to test that view is before the bid, not after the win.