Performance & Payment Bonds · Performance & Payment Bonds

Getting a Copy of the Payment Bond You Are Claiming Against

Most subcontractors who need a payment bond claim start by asking the prime contractor for a copy of the bond. That is a reasonable instinct and it is the slowest available route, because the party you are asking is the party whose surety you are about to claim against.

There is a statutory route that does not go through them.

The right

40 U.S.C. § 3133(a) is the least-used sentence in the Miller Act. It entitles a person who has furnished labor or material for work provided for in a bonded federal contract — on submitting an affidavit that they did so and have not been paid — to a certified copy of the payment bond and the contract itself, from the department secretary or official who awarded the contract, on payment of any actual cost of preparation.

Take the pieces one at a time, because each one is doing work.

The right runs against the Government, not the prime. That is the entire design. A claimant should not need the cooperation of the entity they may sue in order to find out who the surety is.

It is conditioned on an affidavit. Not a request, an affidavit: a sworn statement that you furnished labor or material for the work and have not been paid. That is a low bar for a genuine claimant and a real bar for a competitor fishing for contract documents.

It includes the contract, not just the bond. The contract is often the more useful document, because scope and payment terms are what a dispute is actually about.

There is a cost, and it is a copying cost. The statute contemplates payment of the actual cost of preparation — a duplication charge, not a price on the right.

Why it matters more than it sounds

Three practical things fall out of having the bond in hand early.

You learn who the surety is. Until you have the bond you are dealing with the prime contractor. Once you have it you know the corporate surety that stands behind the obligation and can be addressed directly.

You learn the penal sum. The bond has a ceiling. On a job with several unpaid subcontractors, the size of that ceiling relative to the total unpaid is the single most important fact about your recovery, and it is written on the face of the instrument.

You can address a notice correctly. A second-tier claimant has to give the prime written notice within 90 days of last furnishing under § 3133(b)(2) — and several states go further and specify the channel. Maine’s 14 M.R.S. § 871 requires service by registered or certified mail addressed to the contractor at any place the contractor maintains an office, conducts business, or resides. Knowing the correctly named contracting entity and its addresses before you write is worth more than another week of phone calls.

What it does not do

Requesting the bond does not toll anything. The 90-day notice clock and the one-year suit limit in § 3133(b)(2) and (b)(4) both run from the day you last performed labor or supplied material, and they keep running while you wait for a copy in the mail. If you are close to either deadline, the request is something you do in parallel with the notice, not before it.

It also does not establish your claim. The affidavit says you furnished and were not paid; it is the price of admission to the document, not a filing.

And it is federal. Contracts of the Federal Government are covered; state and local public work is not. Several states have their own document-access provisions and they are not identical — some run through the public body, some through public records law generally, and some say nothing at all.

The state picture, briefly

We have not read the document-access provisions state by state, so this page does not state them. What the state statutes we have read do show is that the surrounding claim mechanics vary enough that the federal habit does not transfer cleanly.

South Carolina’s S.C. Code § 11-35-3030 fixes where suit must be brought — the county or circuit where the construction contract was to be performed. North Dakota’s N.D.C.C. § 48-01.2-10 requires the second-tier notice to be served by registered mail addressed to an office, place of business, or residence. Those are the kinds of details a copy of the bond helps you get right, and they differ from the federal baseline.

The order of operations

If you are unpaid on a bonded federal job and are not yet at a deadline:

  1. Note the date you last performed labor or supplied material. Every clock runs from it.
  2. Submit the § 3133(a) affidavit to the awarding department and ask for the bond and the contract.
  3. Determine whether you are a first-tier or second-tier claimant — whether your contract was with the prime or with one of its subcontractors.
  4. If second tier, send the § 3133(b)(2) notice within 90 days, stating the amount with substantial accuracy and the name of the party you furnished to. Do not wait for the bond to arrive.

Step 2 is the one people skip, and it is the only one that costs nothing.

Frequently asked questions

Can I get a copy of the payment bond on a federal job?
Yes. Under 40 U.S.C. § 3133(a), a person who furnished labor or material for the work and submits an affidavit that they did so and have not been paid is entitled to a certified copy of the payment bond and the contract from the department that awarded it.
Do I need the prime contractor’s permission?
No. The right under § 3133(a) runs against the Government department secretary or official who awarded the contract, not against the prime. That is the point of it — the party you may end up claiming against is not the gatekeeper.
What do I have to submit?
An affidavit that you furnished labor or material for the work and have not been paid. The statute conditions the right on that affidavit, so a bare request is not what it describes.
Is there a charge?
The statute provides that the copy is furnished on payment of any actual cost of preparation, so expect a duplication charge rather than a fee for the right itself.
Does asking for the bond start or extend any deadline?
No. The 90-day notice clock in § 3133(b)(2) and the one-year suit limit in § 3133(b)(4) both run from your last labor or material and are unaffected by whether or when you request the bond.

Do this before the letter, not after

Requesting the bond costs nothing and starts no clock. Doing it early means that if a claim does become necessary you already know the surety, the penal sum and the exact obligee — and you are writing a notice to a named party rather than to whoever answers the phone at the prime contractor’s office.

Where to go next