The One-Year Clock on a Payment Bond Claim

Of all the deadlines on a bonded federal job, the one-year limit is the one most often missed for the least interesting reason: people measure it from the wrong day.

What the statute actually says

40 U.S.C. § 3133(b)(4):

“no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the action.”

The trigger is your own last contribution. Not the date of the invoice. Not the date payment fell due. Not the date the prime told you the money was coming. Not substantial completion, and not final acceptance of the project.

That distinction matters most for exactly the claimant who most needs the bond: a supplier who delivered early on a long job. Deliver the last of your material in month three of a thirty-month contract and your year expires while the job is still going — long before anyone would naturally think of the claim as stale.

Two clocks, not one

The one-year limit is a separate obligation from the notice requirement, and a second-tier claimant is subject to both.

ObligationWho owes itDeadlineRuns from
Written notice to the primeSecond-tier claimants only (40 U.S.C. § 3133(b)(2))90 daysLast labor performed or material supplied
Filing suit on the bondEvery claimant (40 U.S.C. § 3133(b)(4))One yearLast labor performed or material supplied

Both run from the same event, which is convenient, and neither can be satisfied by doing the other. Giving notice does not extend the year. Filing suit does not cure a missing notice.

The states copied the structure, not the details

Because the Miller Act is the model, most state public-works bond statutes look similar at a glance. The details they changed are the ones that decide cases, and three states in our reading show how far the variation goes.

Maine runs the same year but writes an exception into it. Under 14 M.R.S. § 871 an action may not be commenced after one year from the last labor or material,

“except that in the case of a material supplier, when the amount of the claim is not ascertainable due to the unavailability of final quantity estimates, the action may be commenced before the expiration of one year from the date on which the final quantity estimates are determined.”

The same section also fixes the notice to a channel: it must be served by registered or certified mail, postage prepaid, addressed to the contractor at any place the contractor maintains an office, conducts business, or resides.

Oklahoma can give two years instead of one. Under 61 O.S. § 1 no action may be brought after one year from the last labor or material —

“unless a prior claim has been filed within one (1) year from the day on which the labor was performed or material or parts furnished, in which case, no action shall be brought on the bond after two (2) years”

so filing the claim inside the first year buys a second year to sue. That is a materially different position from the federal rule, and it rewards the claimant who files early even if they are not ready to litigate.

North Dakota starts its right of action from the same 90-day non-payment trigger the federal statute uses: under N.D.C.C. § 48-01.2-10, a person who furnished labor or material and has not been paid in full within ninety days after completing the contribution may sue on the bond for the amount unpaid at the time of institution of suit.

The notice channel is not always “written notice”

The federal statute says written notice and stops there. Several states say more.

Maine and North Dakota both specify registered mail (Maine adds certified), and both describe where it must be addressed — an office, a place of business, or a residence. South Carolina, under S.C. Code § 11-35-3030, adds a venue rule to the suit itself: every suit on a payment bond must be brought in the county or circuit where the construction contract was to be performed.

None of that is exotic drafting. It is the legislature deciding that a claimant should not be able to say “I told them” without a record, and it means an email to a project manager may satisfy nobody.

What this page does not do

It does not tell you your deadline. It tells you which sentence sets it, and that the sentence is usually shorter and earlier than people assume.

The federal rules above are the Miller Act and apply to federal contracts. On state or local public work, the state’s own statute governs, and this page quotes only four of them — the states whose provisions we have read in full. On private work there may be no statute at all and the bond form itself sets the terms.

If a deadline is close, that is a question for a construction lawyer in the relevant jurisdiction, not for a page on the internet.

Frequently asked questions

How long do I have to sue on a federal payment bond?
One year. 40 U.S.C. § 3133(b)(4) requires the action to be brought “no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the action.”
Does the year run from when I was supposed to be paid?
No. It runs from the day you last performed labor or supplied material. The date of your invoice, the date payment became due, and the date the project was accepted are all irrelevant to this clock under § 3133(b)(4).
Is the 90-day notice the same as the one-year deadline?
No, they are separate and both can apply. A second-tier claimant must give the prime written notice within 90 days of last furnishing under § 3133(b)(2), and separately must file suit within one year under § 3133(b)(4).
Do state public-works bonds use the same one-year rule?
Several use one year but measure it differently. Maine runs one year from the last labor or material under 14 M.R.S. § 871, with an express exception for material suppliers whose claim is not ascertainable until final quantity estimates. Oklahoma’s 61 O.S. § 1 allows two years for suit where a claim was filed within the first year.
What happens if I miss the deadline?
The right of action is lost. These are conditions on the statutory remedy rather than ordinary limitation defenses to be argued about, so the strength of the underlying debt does not rescue a late claim.

The date worth writing down

The single most useful record a subcontractor or supplier can keep on a bonded job is the date of its own last delivery or last hour worked, per contract, in writing. Every deadline in this page runs from that date, and it is the one date nobody thinks to capture while it is still easy to establish.